BRIEFING NOTE
Subject: Denny Town Centre Regeneration – update
Date 7 September 2015
1.0 Introduction
1.1 The purpose of this report is to provide an update
on the status of the Denny Town Centre Regeneration Project
2.0 Phase 1
2.1 Work is underway on the first phase of the new
town centre. Clark Contracts Ltd are the
Phase 1 main contractor and has confirmed that works
are proceeding to programme (see photo below)
Denny Phase 1 – works to date (photo taken
22 Sept 2015)
|
Phase 1 Building
· Drainage diversion works complete
· Building footprint excavations to formation level
complete
· Foundations being prepared including steel reinforcement and concrete
blinding layer
·
Concrete foundation pads and strip foundation
setting out complete
·
Foundations and retaining wall erection completed
·
Steel Frame upper floor slab erection commenced and
will continue through October 2015
Davies Row Car Park
· Existing tarmac surfacing removed from site
· Existing retaining walls reduced to grounds
·
Excavations
to reduced levels ongoing
·
Davies Row car park drainage ongoing
3.0 Phase 2 Development
3.1 The Phase 2 site was remarketed by SGM,
commercial agents. A report was submitted
to the Council’s Executive on the 9 June on the results of the marketing
exercise. One offer was received, from County Properties
(Northern) Limited, a privately owned investment and development company with a
large, mixed portfolio throughout the UK.
3.2 The Executive agreed that the Council
should approach County Properties requesting that they review their
submission for the scheme to better fit the requirements of the brief. Discussions with County Properties
are continuing, seeking these revisions and will be presented back to the
Executive once finalised by the developer.
4.0 Phase 3 Development
4.1 A report on the conclusions from the recent
‘Charrette’ consultation was presented by Icecream Architecture to the community on the 21 August in the Denny Community Education Centre. A Denny Charrette Fund of £10,000 has been
set up and to date 7 applications have been received conveying project
ideas. These ideas are currently with Icecream Architecture who will
assess the submissions and make recommendations to the community panel for
funding approval. Further details on this process are available from
Jacquie McArthur at the Denny Project Office.