FALKIRK COUNCIL
BRIEFING NOTE
From: Douglas Duff, Head of Economic Development & Environmental Services
Subject: Denny Town Centre Regeneration – update
Date 4th April 2016
1.0 Introduction
1.1 The purpose of this report is to provide an update on the status of the Denny Town Centre Regeneration Project
2.0 Phase 1
2.1 Work is underway on the first phase of the new town centre. Clark Contracts Ltd is the Phase 1 main contractor and has confirmed that works are proceeding to programme (see photo below)
Denny Phase 1 – works to date
The works carried out to date include:
Phase 1
· Blockwork ongoing
· Scaffold internally and externally ongoing
· Continue laying slates on both elevations
· Continue electrical containment
· Continue with ventilation ducting
· Continue constructing electrical cupboards and WCs
· Continue with Plumbing
· Continue with facing brick on external leaf
· Completed cill supports
· Commenced outer skin of blockwork
· Commenced flat roof works
Phase 1 Public Art Proposals
2.2 Work is underway to commission artists for the 5 public art projects outlined in the previous briefing. These commissions will be developed and tendered competitively as five separate artist briefs. The overall management of this process will be undertaken by Falkirk Council. A programme for the commissions will follow.
Public Wi-fi
2.3 The Council in collaboration with BT hope to deliver a public Wi-Fi scheme as part of the phase 1 plans.
2.4 Foundation Scotland is now accepting applications for grants and constituted groups and organisations working to benefit those living in the Denny & District area. Application and guidance material is available here - https://www.foundationscotland.org.uk/programmes/denny-and-district/.
3.0 Phase 2 Development
3.1 As agreed through the Council’s Executive on the 23 February 2016, a formal legal agreement is being prepared between Falkirk Council and County properties in the disposal of the Phase 2 site subject to an agreement on development timescale and commitment from B & M.
4.0 Phase 3 Development
4.1 Following the community presentation on the conclusions from the Denny Charrette consultation, printed copies of the final report are available at key public buildings in the town. Printed copies are available on request to 01324 590973. The Denny Charrette Fund via Foundation Scotland is currently supporting a number of local projects within the town centre.
Tuesday, 26 April 2016
Monday, 25 April 2016
Morning Andrew
I
can confirm that the TSB branch in Denny will be closing in early July
as a result of the Church Walk regeneration project and we haven’t found
a suitable replacement site. Please see below for our statement and if
you need anything else, please do let me know.
Many thanks
Claire
"As
a result of the forthcoming regeneration of Denny town centre we have
to close
our Denny branch. While this redevelopment is an exciting opportunity
for Denny, it does not look likely that we will have a replacement for
the current TSB branch.
“We
realise that this may well be unwelcome news and moving out of Denny is
not something that we were planning to do had this redevelopment
not forced the issue. Our nearest branch to Denny is Falkirk, and we
hope people will find time to pop in once our Denny branch closes.”
Claire Miller
Senior Manager, Media Relations, TSB
T: 020
7003 9363 / 9369 | M:
07900 276400 | E: claire.miller@tsb.co.uk|
@TSB_News
| LinkedIn
(TSB)
Over a third of Brits cannot name a local charity in their area.
Find out more here.
Subscribe to:
Posts (Atom)