Date: Thu, 25 Feb 2016 15:05:13 +0000
Subject: RE: Denny Roundabout
Mr Wallace,
I refer to your email dated 22 February 2016 and would respond as follows.
The
roadworks are being carried out by Allma Construction on behalf of
Avant Homes. Earlier this week, Avant Homes confirmed the following
programme.
· 24 Feb to 26 Feb – Scottish Power expected onsite to divert overheads
· 29 Feb or 1 March – Scottish Water expected onsite to inspect the diverted main
· 2 March – Existing 3 way TTLs come down
· 10 March – TTLs back up to allow connection to main
· ?
March – TTLs removed, utilities broadly completed (with exception of
gas?) Allma onsite to complete roadworks using minimal TM where required
· End March – roadworks broadly completed, signing and lining possibly outstanding
Please contact Avant Homes on 01786 477777 to obtain marketing photographs of the site.
I trust this response addresses your enquiry.
Regards,
Craig Russell
Senior Roads Development Officer
Falkirk Council Development Services
Abbotsford House
Davids Loan
Falkirk FK2 7YZ
01324 50 4732